CBI arrests South Eastern Railway engineer while accepting ₹4 lakh bribe at Howrah stationCJP calls off NEET protest after Dharmendra Pradhan resigns; government accepts key demandsNo ‘out-of-turn’ VIP or VVIP darshan during Shravani Mela, says minister Sudivya KumarNilamber Pitamber University gives two colleges until July 30 to restore science faculty affiliationDharmendra Pradhan resigns as Union Education Minister amid NEET protest row, student agitationJharkhand Weather: Active monsoon to bring heavy rain till July 30; rainfall deficit narrows to 27%From Kumirmudi to national glory: Ravi Raj Murmu’s journey inspires a new generation of tribal storytellers1. Jharkhand HC sends strong message on marriage, rejects four divorce appeals in one day 2. CM Hemant Soren orders crackdown on illegal liquor trade, fast-tracks excise recruitment in Jharkhand and more stories

12 SECL coal projects hit by delays due to environmental and land hurdles

  New Delhi, Oct 24: South Eastern Coalfields Limited (SECL), a key arm of Coal India Limited (CIL), is currently experiencing delays…

12 SECL coal projects hit by delays due to environmental and land hurdles

 

New Delhi, Oct 24: South Eastern Coalfields Limited (SECL), a key arm of Coal India Limited (CIL), is currently experiencing delays in 12 of its ongoing coal mining projects. These setbacks are primarily due to delays in obtaining environmental clearances and issues related to land possession. The delay comes at a time when the government is intensifying efforts to increase domestic coal production to reduce reliance on imports.

Advertisement
Advertisement

Details of Delayed Projects

Out of the 30 ongoing projects under SECL, 12 projects are facing schedule slippages while 18 are progressing as planned. The delayed projects vary in scale and investment:

  • Three projects have costs exceeding Rs 500 crore.
  • Five projects cost between Rs 150 crore and Rs 500 crore.
  • Two projects fall in the Rs 100 crore to Rs 150 crore range.
  • One project costs between Rs 50 crore and Rs 100 crore.
  • Another project falls between Rs 20 crore and Rs 50 crore.

Notable projects experiencing delays include the Amadand Open Cast Mine, Amgaon Open Cast Project, and Vijay West Underground Mine.

Stay informed. Get Jharkhand's top stories in your inbox.

Free. No spam. Unsubscribe anytime.

Also Read- PM Modi sounds poll bugle from Samastipur, says ‘Bihar wants NDA again’

Monitoring and Oversight Mechanisms

Large projects costing Rs 500 crore or more are closely monitored by the Ministry of Coal through monthly project review meetings. Projects valued at Rs 150 crore and above are tracked via an online computerized monitoring system maintained by the Ministry of Statistics and Programme Implementation (MoSPI). These measures aim to enhance transparency and expedite project implementation.

SECL’s Extensive Project Portfolio

SECL currently has 73 major coal projects approved, with an ultimate capacity target of 302.75 million tonnes per annum and a sanctioned capital investment of Rs 44,571 crore. Out of these, 30 projects are ongoing, 38 projects have been completed successfully, and five underground blocks are operational mines.

Advertisement
Advertisement

Production Performance and Reserves

In the financial year 2024-25, SECL produced 167.487 million tonnes of coal. The company’s coal reserves are predominantly located across the states of Chhattisgarh and Madhya Pradesh, making it a critical supplier in India’s energy sector.

Also Read- 20 killed as bus catches fire after collision in Andhra’s Kurnool

About South Eastern Coalfields Limited (SECL)

South Eastern Coalfields Limited is a Mini Ratna public sector enterprise under Coal India Limited, headquartered in Bilaspur, Chhattisgarh. SECL is one of the largest coal-producing companies in India, focusing on the exploration, extraction, and supply of coal to meet the country’s growing energy demands. The company plays a vital role in supporting India’s energy security and industrial growth through sustainable and efficient mining practices.

(For more such stories you may visit indianmasterminds.com)

Advertisement
Advertisement
More from Breaking
CBI arrests South Eastern Railway engineer while accepting ₹4 lakh bribe at Howrah station

CBI arrests South Eastern Railway engineer while accepting ₹4 lakh bribe at Howrah station

July 25, 2026
CJP calls off NEET protest after Dharmendra Pradhan resigns; government accepts key demands

CJP calls off NEET protest after Dharmendra Pradhan resigns; government accepts key demands

July 25, 2026
No ‘out-of-turn’ VIP or VVIP darshan during Shravani Mela, says minister Sudivya Kumar

No ‘out-of-turn’ VIP or VVIP darshan during Shravani Mela, says minister Sudivya Kumar

July 25, 2026

Stay informed. Get Jharkhand's top stories in your inbox.

Free. No spam. Unsubscribe anytime.

About the Author

Suman Shrivastava