East Singhbhum schools to remain closed on October 28 and 29 amid cyclone warningCyclone Arnab impacts Jharkhand; rain and gusty winds sweep KolhanPalamu civil surgeon suspends Jeevan Jyoti Nursing Home’s registration for three daysModel Degree College in Palamu awaits academic take-off nearly two years after takeoverCM Hemant Soren felicitates winners at All India Police Archery Championship in RanchiSona Devi University launches vigilance awareness week with focus on integrityVijaya Gardens Chitransh Parivaar to celebrate Chitragupta Puja on Nov. 11Tata Steel surveys nearly 4.9 lakh houses in intensified dengue prevention drive

SC quashes blacklisting in Jharkhand contractor case

  Ranchi, April 2: The Supreme Court has set aside the blacklisting of M/s A.K.G. Construction and Developers Pvt. Ltd. in a…

SC quashes blacklisting in Jharkhand contractor case

 

Ranchi, April 2: The Supreme Court has set aside the blacklisting of M/s A.K.G. Construction and Developers Pvt. Ltd. in a Jharkhand case, while upholding the termination of its contract over a collapsed water reservoir project.

The ruling clarifies that blacklisting cannot automatically follow contract termination and must comply with principles of natural justice.

Case linked to water tower collapse

The contractor was awarded a project in March 2023 to build an Elevated Service Reservoir (ESR) in Jharkhand. In June 2024, the structure’s top dome collapsed.

Stay informed. Get Jharkhand's top stories in your inbox.

Free. No spam. Unsubscribe anytime.

While the firm blamed a cyclone and offered to rebuild the structure, multiple inquiries—including expert inputs—found negligence and poor-quality construction.

Based on these findings, the state terminated the contract and blacklisted the company for five years.

Advertisement
Advertisement

ALSO READ: A mother, a ritual, and a girl child lost: Inside Jharkhand’s shocking human sacrifice case

SC: Blacklisting process legally flawed

A bench of Justices Pamidighantam Sri Narasimha and Alok Aradhe upheld the termination but struck down the blacklisting, citing procedural lapses.

The Court noted:

Advertisement
Advertisement
  • No specific show-cause notice for blacklisting
  • Lack of application of the mind
  • Violation of natural justice principles

It observed that blacklisting is a “stigmatic and exclusionary” action and cannot be imposed mechanically.

Not an automatic consequence

The Court emphasised that termination and blacklisting operate in different domains:

  • Termination affects existing contracts
  • Blacklisting impacts future business opportunities

Therefore, authorities must take an independent and reasoned decision before blacklisting any contractor.

Considering the time already elapsed, the Court ruled that the blacklisting order will cease with immediate effect, instead of directing a fresh process.

 

More from Breaking
East Singhbhum schools to remain closed on October 28 and 29 amid cyclone warning

East Singhbhum schools to remain closed on October 28 and 29 amid cyclone warning

October 27, 2026
Cyclone Arnab impacts Jharkhand; rain and gusty winds sweep Kolhan

Cyclone Arnab impacts Jharkhand; rain and gusty winds sweep Kolhan

October 27, 2026
Palamu civil surgeon suspends Jeevan Jyoti Nursing Home’s registration for three days

Palamu civil surgeon suspends Jeevan Jyoti Nursing Home’s registration for three days

October 27, 2026

Stay informed. Get Jharkhand's top stories in your inbox.

Free. No spam. Unsubscribe anytime.

About the Author

Suman Shrivastava