Woman with child rescued from attempt to jump into Subarnarekha River in JamshedpurSona Devi University concludes Hindi pakhwada, calls for Hindi-technology integration for global reachJamshedpur Gurudwara committee seeks daily Jallianwala Bagh Express between Tatanagar and AmritsarJharkhand HC directs RMC to reconsider notice against Argora banquet hall, bars sealingJustice Aparesh Kumar Singh elevated to Supreme Court, major milestone for Jharkhand Judiciaryझारखंड भाजपा प्रभारी गजेंद्र सिंह पटेल ने जनजातीय समाज से जुड़ाव मजबूत करने का संकल्प दोहरायाJharkhand BJP in-charge Gajendra Singh Patel pledges stronger tribal outreachIIT-ISM Professor Ram Madhab Bhattacharjee receives prestigious MGMI Award

SC quashes blacklisting in Jharkhand contractor case

  Ranchi, April 2: The Supreme Court has set aside the blacklisting of M/s A.K.G. Construction and Developers Pvt. Ltd. in a…

SC quashes blacklisting in Jharkhand contractor case

 

Ranchi, April 2: The Supreme Court has set aside the blacklisting of M/s A.K.G. Construction and Developers Pvt. Ltd. in a Jharkhand case, while upholding the termination of its contract over a collapsed water reservoir project.

The ruling clarifies that blacklisting cannot automatically follow contract termination and must comply with principles of natural justice.

Case linked to water tower collapse

The contractor was awarded a project in March 2023 to build an Elevated Service Reservoir (ESR) in Jharkhand. In June 2024, the structure’s top dome collapsed.

Stay informed. Get Jharkhand's top stories in your inbox.

Free. No spam. Unsubscribe anytime.

While the firm blamed a cyclone and offered to rebuild the structure, multiple inquiries—including expert inputs—found negligence and poor-quality construction.

Based on these findings, the state terminated the contract and blacklisted the company for five years.

Advertisement
Advertisement

ALSO READ: A mother, a ritual, and a girl child lost: Inside Jharkhand’s shocking human sacrifice case

SC: Blacklisting process legally flawed

A bench of Justices Pamidighantam Sri Narasimha and Alok Aradhe upheld the termination but struck down the blacklisting, citing procedural lapses.

The Court noted:

Advertisement
Advertisement
  • No specific show-cause notice for blacklisting
  • Lack of application of the mind
  • Violation of natural justice principles

It observed that blacklisting is a “stigmatic and exclusionary” action and cannot be imposed mechanically.

Not an automatic consequence

The Court emphasised that termination and blacklisting operate in different domains:

  • Termination affects existing contracts
  • Blacklisting impacts future business opportunities

Therefore, authorities must take an independent and reasoned decision before blacklisting any contractor.

Considering the time already elapsed, the Court ruled that the blacklisting order will cease with immediate effect, instead of directing a fresh process.

 

More from Breaking
Woman with child rescued from attempt to jump into Subarnarekha River in Jamshedpur

Woman with child rescued from attempt to jump into Subarnarekha River in Jamshedpur

October 5, 2026
Sona Devi University concludes Hindi pakhwada, calls for Hindi-technology integration for global reach

Sona Devi University concludes Hindi pakhwada, calls for Hindi-technology integration for global reach

October 5, 2026
Jamshedpur Gurudwara committee seeks daily Jallianwala Bagh Express between Tatanagar and Amritsar

Jamshedpur Gurudwara committee seeks daily Jallianwala Bagh Express between Tatanagar and Amritsar

October 5, 2026

Stay informed. Get Jharkhand's top stories in your inbox.

Free. No spam. Unsubscribe anytime.

About the Author

Suman Shrivastava