‘Valid ticket is enough’: Jharkhand HC directs Railways to pay ₹8 lakh in train fall death case1. Jharkhand CM sets 15-day deadline to operationalise University Service Commission 2. Jharkhand HC again raps State over bureaucratic lethargy, dismisses 559-day delayed appeal in Anganwadi Sevika case and more storiesRanchi gears up to host Durand Cup 2026 matches for the first timeJharkhand CM sets 15-day deadline to operationalise University Service CommissionJharkhand HC sets aside rejection of life convict’s premature release pleaBJP says Jharkhand govt recycled Davos investment dealsBear attacks on humans continue in Palamu Tiger Reserve; five injured in a week amid monsoon foragingXLRI, Dale Carnegie India partner to equip future leaders with AI-era leadership skills

Jharkhand ACB files FIR in RIMS land scam

 Ranchi, January 6: Acting on strict directions of the Jharkhand High Court, the Anti-Corruption Bureau (ACB) has registered an FIR at its…

Jharkhand ACB files FIR in RIMS land scam

 Ranchi, January 6: Acting on strict directions of the Jharkhand High Court, the Anti-Corruption Bureau (ACB) has registered an FIR at its Ranchi unit and initiated an investigation into large-scale illegal encroachment on land belonging to the Rajendra Institute of Medical Sciences (RIMS).

The FIR was lodged on Tuesday following orders of a Division Bench comprising Chief Justice Tarlok Singh Chauhan and Justice Sujit Narayan Prasad, which had earlier directed criminal action against officials whose collusion enabled illegal constructions on government land acquired for RIMS more than five decades ago.

The High Court had made it clear that while illegal encroachments must be removed, residents whose houses are being demolished would be compensated. However, the compensation amount will not be borne by the State exchequer and will instead be recovered from the guilty officials and builders responsible for the illegal constructions.

Officials Under ACB Scanner

According to the court’s directions, the ACB probe will cover officials who manipulated revenue records to mutate and register government land illegally, issued rent receipts and no-objection certificates, sanctioned building plans, and facilitated multi-storey constructions on acquired RIMS land.

Stay informed. Get Jharkhand's top stories in your inbox.

Free. No spam. Unsubscribe anytime.

The investigation will include revenue officials, Circle Officers, municipal authorities, planning bodies and other regulatory agencies whose actions allowed private ownership claims to be created on land vested in the State.

Background: Land Acquired in 1964–65

In its detailed judgment delivered on December 21, the Jharkhand High Court traced the controversy to land acquisition proceedings conducted in 1964–65 for establishing RIMS, including hospital buildings and hostels. The acquisition was completed under the Land Acquisition Act, 1894, compensation was paid to all landowners, and the land vested absolutely in the State.

Advertisement
Advertisement

Despite this, the Court found that illegal registrations, mutations, rent receipts, non-encumbrance certificates, building plan sanctions and even RERA approvals were granted over the years, leading to widespread construction within the RIMS campus.

Over 7 Acres Encroached

The issue surfaced in a Public Interest Litigation pending since 2018. An inquiry conducted by JHALSA Member Secretary Kumari Ranjana Asthana, on the Court’s directions, found encroachments over nearly seven acres of RIMS land.

The Court noted the presence of unauthorised temples, shops, huts, parks, commercial establishments and multi-storey residential buildings within the campus, posing serious risks to hospital hygiene, security and patient safety, especially near the girls’ hostel.

Advertisement
Advertisement

Based on these findings, the Court ordered the removal of encroachments on December 3, granting 72 hours to vacate.

Claims Rejected, Law Settled

The Bench rejected ownership claims based on old khatiyan records, rent receipts, sale deeds and CNT Act permissions, holding that no document can revive title once land is lawfully acquired. It also rejected pleas under Section 24(2) of the 2013 Land Acquisition Act, relying on the Supreme Court’s ruling in Indore Development Authority v. Manoharlal (2020).

Wider Accountability

The Court also expressed concern over banks that sanctioned loans on acquired land and RIMS authorities who failed to act despite encroachments. Banks have been directed to conduct internal inquiries.

While refraining from ordering a CBI probe, the Court has kept that option open depending on the outcome of the ACB investigation.

The FIR marks the first concrete step towards fixing accountability in what the Court described as a systemic failure of land governance.

 

 

 

More from Breaking
‘Valid ticket is enough’: Jharkhand HC directs Railways to pay ₹8 lakh in train fall death case

‘Valid ticket is enough’: Jharkhand HC directs Railways to pay ₹8 lakh in train fall death case

July 14, 2026
1. Jharkhand CM sets 15-day deadline to operationalise University Service Commission 2. Jharkhand HC again raps State over bureaucratic lethargy, dismisses 559-day delayed appeal in Anganwadi Sevika case and more stories

1. Jharkhand CM sets 15-day deadline to operationalise University Service Commission 2. Jharkhand HC again raps State over bureaucratic lethargy, dismisses 559-day delayed appeal in Anganwadi Sevika case and more stories

July 13, 2026
Ranchi gears up to host Durand Cup 2026 matches for the first time

Ranchi gears up to host Durand Cup 2026 matches for the first time

July 13, 2026

Stay informed. Get Jharkhand's top stories in your inbox.

Free. No spam. Unsubscribe anytime.

About the Author

Suman Shrivastava