If IAS officers can go to jail, why not IPS officers? Babulal Marandi questions police accountabilityBabulal Marandi meets family of tribal rape victim in Panki, demands security and strict actionJharkhand HC orders removal of low-hanging hoardings in Ranchi over road safety concernsJharkhand HC quashes cancellation of Awadh Dental College’s essentiality certificate‘Jado se jude rahiye aur udaan bhariye’: Nesha Oraon calls for balancing tribal roots with modern aspirationsSona Devi University induction programme urges students to embrace innovation, ethical leadershipJharkhand braces for heavy rain; I-Day celebrations may turn wetIIT (ISM) researchers develop eco-friendly sand substitute from fly ash and plastic waste

Jharkhand News: Patratu Super Thermal Power project’s first 800 MW unit synchronized with grid

MANOJ SINHA   Ramgarh, March 11: In a significant achievement for India’s energy sector, Patratu Vidyut Utpadan Nigam Limited (PVUNL) successfully synchronized…

Jharkhand News: Patratu Super Thermal Power project’s first 800 MW unit synchronized with grid

MANOJ SINHA

 

Ramgarh, March 11: In a significant achievement for India’s energy sector, Patratu Vidyut Utpadan Nigam Limited (PVUNL) successfully synchronized the first 800 MW unit of the Patratu Super Thermal Power Phase-I Project with the grid at 9:14 a.m.

This milestone marks a major step toward strengthening Jharkhand’s energy infrastructure and ensuring a stable power supply for the nation.

Stay informed. Get Jharkhand's top stories in your inbox.

Free. No spam. Unsubscribe anytime.

R.K. Singh, CEO of PVUNL, expressed gratitude to the PVUNL, NTPC and BHEL teams for their tireless efforts, dedication, and perseverance in overcoming challenges to achieve this synchronization.

Also Read- Mahesh Gupta joins National Fertilizers Limited as Director (Marketing)

He also acknowledged the Project, O&M/Commissioning, and Services departments of PVUNL and BHEL, along with Associates, support staff, and other stakeholders for their invaluable contributions.

Advertisement
Advertisement

Looking ahead, PVUNL’s immediate priority is to achieve the Commercial Operation Date (COD) for Unit #1 within this financial year. Additionally, the company is committed to commissioning the remaining two units of Phase-I in FY 2025-26, further enhancing India’s power generation capacity.

“This achievement reflects the strategic planning, collaboration, and dedication of all involved in the Patratu Super Thermal Power Project,” said R. K. Singh. He also thanked the NTPC senior management and JBVNL for their support and added, “We remain focused on delivering sustainable and efficient power for the nation.”

Advertisement
Advertisement

Also Read- Jharkhand doctors’ bodies furious over six-month salary delay for SNMMCH Senior Residents

More from Breaking
If IAS officers can go to jail, why not IPS officers? Babulal Marandi questions police accountability

If IAS officers can go to jail, why not IPS officers? Babulal Marandi questions police accountability

August 13, 2026
Babulal Marandi meets family of tribal rape victim in Panki, demands security and strict action

Babulal Marandi meets family of tribal rape victim in Panki, demands security and strict action

August 13, 2026
Jharkhand HC orders removal of low-hanging hoardings in Ranchi over road safety concerns

Jharkhand HC orders removal of low-hanging hoardings in Ranchi over road safety concerns

August 13, 2026

Stay informed. Get Jharkhand's top stories in your inbox.

Free. No spam. Unsubscribe anytime.

About the Author

Suman Shrivastava