JPSC postpones Combined Civil Services Main Exam 2025, defers all upcoming recruitment tests1. 14th JPSC Exam Row: CID arrests five, Governor accepts Chairman’s resignation amid protests 2. Jharkhand signs MoU with SRFTI to establish Film and Television Institute and more stories‘Grave Illegality’: Jharkhand HC orders State govt to pay ₹3 lakh for illegal vehicle auctionBabulal Marandi demands CBI probe into JPSC scam, alleges ‘mastermind’ is being shielded14th JPSC Exam Row: CID arrests five, Governor accepts Chairman’s resignation amid protestsIIT (ISM) Dhanbad conducts executive programme on data analytics for SAIL Bokaro executivesJharkhand braces for 5-day rain spell as IMD forecasts active Monsoon phaseJharkhand to launch eastern India’s first government-run Aircraft Maintenance Engineering Institute

Daltonganj Medical College’s 500-bed hospital still incomplete after 6 years

  Daltonganj, November 30: The 500-bed hospital at Medinirai Medical College in Daltonganj remains unfinished even after six years, with no confirmed date…

Daltonganj Medical College’s 500-bed hospital still incomplete after 6 years

 

Daltonganj, November 30: The 500-bed hospital at Medinirai Medical College in Daltonganj remains unfinished even after six years, with no confirmed date for operations to begin in 2026. Major gaps in water supply, electricity, sewer treatment, and biomedical waste systems continue to delay the project.

Advertisement
Advertisement

An underground sump meant for water storage is not adequate for the hospital, residential complexes, and hostels. The 8-lakh-gallon capacity falls far short of the total requirement. A proposed substation for electricity is also progressing slowly, leaving the hospital’s functioning uncertain.

Repeated Deadlines Missed by Construction Agency

The construction agency—known for handling large multi-crore projects—has repeatedly missed deadlines. Each time, it claims completion “by June” or “by December,” but none of these assurances have materialized.

Stay informed. Get Jharkhand's top stories in your inbox.

Free. No spam. Unsubscribe anytime.

In January 2025, then Principal Secretary of Health Ajoy Kumar Singh, now Additional Chief Secretary, inspected the site and directed the agency to finish the hospital by June 2025. The agency asked for an extension until August 2025, prompting Singh to warn of penalties of up to 8% for continued delays. Despite this, no visible progress followed.

Sand Crisis and Material Shortages Slow Progress

The construction agency cites several problems: a severe sand crisis, issues with brick quality, shortage of stone chips, lack of water, and overhead 11 kV electric lines near the site.

Advertisement
Advertisement

Sand is being brought from Dehri and Sherghati in Bihar, making the process costly and slow. Local sand is cheaper but not legally available. “We pay royalty and GST. We cannot buy stolen sand,” said a functionary of the agency. The project requires 500 tonnes of sand, which local suppliers cannot provide.

Closure of illegal stone-crushing units has also disrupted the supply chain for stone chips.

Advertisement
Advertisement

Long Delays Since 2017 Tender and COVID Halt

The tender for the project was issued in 2017, but work only began in December 2020 after delays in obtaining mandatory NoCs. The COVID pandemic further halted progress.

As of now, none of the floors of the G+6 building, whose construction began in December 2019, are ready.

Hopes of Partial Handover by June 2026

MMCH Principal Dr. P. N. Mahto said the agency has assured him that four storeys will be handed over by June 2026. “Interior fittings are going on. A large workforce is working on the ground floor and four floors above it,” he said.

Once these floors are ready, outpatient and emergency OPD services can begin.

Exterior Tiles Falling Off; Texture Paint Suggested

Tiles installed on the exterior walls have started falling due to temperature-related adhesive failure. The construction agency has proposed replacing the tiles with texture painting to avoid injuries and further damage.

 

More from Breaking
JPSC postpones Combined Civil Services Main Exam 2025, defers all upcoming recruitment tests

JPSC postpones Combined Civil Services Main Exam 2025, defers all upcoming recruitment tests

July 22, 2026
1. 14th JPSC Exam Row: CID arrests five, Governor accepts Chairman’s resignation amid protests 2. Jharkhand signs MoU with SRFTI to establish Film and Television Institute and more stories

1. 14th JPSC Exam Row: CID arrests five, Governor accepts Chairman’s resignation amid protests 2. Jharkhand signs MoU with SRFTI to establish Film and Television Institute and more stories

July 22, 2026
‘Grave Illegality’: Jharkhand HC orders State govt to pay ₹3 lakh for illegal vehicle auction

‘Grave Illegality’: Jharkhand HC orders State govt to pay ₹3 lakh for illegal vehicle auction

July 22, 2026

Stay informed. Get Jharkhand's top stories in your inbox.

Free. No spam. Unsubscribe anytime.

About the Author

thejharkhandstory.co.in